United Airlines Hangar

scope of work

  • Over 200+ H-Piles Installed
  • Piles Over 70'+ Deep
  • 15,900 Feet of Pile Installed
  • Dynamic Pile Testing

SERVICES

Deep Foundation

WORK COMPLETED

March 2019

Download Project Page

Project Summary

Over 200 driven piles were installed at O’Hare International Airport as a deep foundation for a new United Airlines hangar. Stalworth mobilized two cranes and crews to meet schedule demands and maximize production. Dense gravel and stiff clay layers reaching 80 blows/ft created challenges during pile driving and were remedied by Stalworth and GRL Engineers, who were brought onto the project for dynamic pile testing.